The Umm Al Hayman Wastewater Project/ Kuwait

Overview: Key Facts

  • Employer: Ministry of Public Works
  • Transaction Advisors: HSBC / Norton Rose / Fichtner
  • Buyers Engineer: Fichtner/Germany
  • Bidder: Consortium WTE Wassertechnik GmbH / International Financial Advisors K.S.C.C.
  • Contract type: combination of BOT and DBO model
    * BOT (WWTP, ESO, Plant relating facilities, ESF)
    * DBO (ROD works, WWPS, WWTS, TADS)
  • Capacity / Size (BOT): Plant: 1,702,128 PE / Qd = 500,000 m3/d
    ESO: 3.5 km (onshore/DN 2,400) and 2.0 km (offshore/DN 2,200)
  • Capacity / Size (DBO): WWPS Egailah (extension from 2.8 m3/s to 8.3 m3/s); ESF at Egailah PS: 132 kV substation
    WWPS SAA (new construction; 2.18 m3/s); WWPS UAH (refurbishment)
    about 450 km WWTS , TSETS and TSEDN (diameter up to DN 1600),
    TSE pumping station at UAH plant
    TSE strategic reservoirs (7 pcs.: V = 40,000 — 160,000 m3) incl. TSE pumping stations
    TSE secondary reservoirs (32 pcs.: V = 2,000 — 3,000 m3) inc l. TSE pumping stations
Timeline until today:
  • Tender publishing date: 18.11.2015
  • Bid submission: 19.09.2016
  • Financial Opening: 16.03.2017
  • Preferred Bidder Notice: 28.08.2017
  • Preferred Bidder Letter: 20.11.2017
  • signing of letter agreement, etc.: 04.11.2018
  • Start of O&M contract for existing facilities: 01.04.2019
  • Effective Date: 23.01.2020
  • Closing Date (expected): April 2020